Page 162 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 162

Software Project Management




                    Notes                  The sequence of activities whose early schedule and late schedule are the same
                                           The sequence of activities with zero slack or float.
                                   The activities that define the critical path are called critical path activities. Any delay in a critical
                                   path activity will delay the completion of the project by the amount of delay in that activity.
                                   Critical path activities represent sequences of activities that warrant the project manager’s special
                                   attention.

                                   Earliest Start Time (ES) and Early Finish Time (EF)

                                   The Earliest Start (ES)  time for an  activity is the earliest time  at which all of its  predecessor
                                   activities have been completed and the subject activity can begin. The ES  time can be set  as
                                   follows:
                                      The ES time of an activity with no predecessor activities is arbitrarily set to 1, the first day
                                       on which the project is open for work.

                                      The ES time of activities with one predecessor activity is determined from the earliest finish
                                       (EF) time of the predecessor activity.

                                      The ES time of activities having two or more predecessor activities is determined from the
                                       latest of the EF times of the predecessor activities.
                                      The ES can also be used to calculate the earliest finish time of an activity. The earliest finish
                                       (EF) of an activity  is calculated  as [(ES  + Duration)  – One  time unit]. The reason  for
                                       subtracting the one time unit is to account for the fact that an activity starts at the beginning
                                       of a time unit (hour, day, and so forth) and finishes at the end of a time unit. In other words,
                                       a one-day activity, starting at the beginning of a day, begins and ends on the same day.


                                          Example: Understand the Dependencies and Network Schedule
                                   Look at Figure 8.6 and note that:

                                      Activity E has only one predecessor, activity C. The EF for activity C is the end of day 3.
                                       Because it is the only predecessor of activity E, the ES of activity E is the beginning of day 4.
                                      Activity D has two predecessors, activity B and activity C. When there are two or more
                                       predecessors, the ES of the successor, activity D in this case, is calculated based on the
                                       maximum of the EF dates of the predecessor activities. The EF dates of the predecessors are
                                       the end of day 4 and the end of day 3. The maximum of these is 4, and therefore, the ES of
                                       activity D is the morning of day 5.

                                      Similarly, the EF and ES for other activities may also be calculated.
                                                           Figure  8.6:  Forward Pass  Calculations




















          156                               LOVELY PROFESSIONAL UNIVERSITY
   157   158   159   160   161   162   163   164   165   166   167