Page 221 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 221

Unit 11: Resource Allocation




                                                                                                Notes


             Notes  However, it is also important to ensure that the resource limit is not exceeded and
             the technical relationships in the project network are not altered.

          Resource Constraints

          The most important resources that project managers have to plan and manage on day-to-day
          basis are people, machines, materials, and working capital. Obviously, if these resources are
          available in abundance then the project could be accelerated to achieve shorter project duration.
          On the other hand, if these resources are severely limited, then the result more likely will be a
          delay in the project completion time. Depending on the type of resources, the costs of providing
          an abundance of such resources to accelerate project completion time can be very high. However,
          if resources are readily available  and excess premiums are  not incurred to use  them on the
          project, then project cost should be low, as some project costs are resource related while others
          are likely to be time dependent. In general, projects with a shorter duration are less expensive.
          The longer the duration of the project, the higher will be overall project cost due to the increase
          in fixed costs such as overheads. The reality is that as long as the work on a project is ongoing it
          will  continue to  draw resources into its orbit. Whatever the parameters  of the project, it  is
          unlikely that the relationship between cost and duration is linear. For any particular project, the
          decision to place the project on the curve between the point of least duration with its associated
          higher resource requirements and a point of increased duration with its associated lower resource
          requirements depends on the particular parameters of the project.

          When a project plan is first devised it is likely that the plan will identify peaks of resource requirements.
          However, given the finite nature of resource availability, it may be impractical to meet such peak
          resource needs. Ideally, there should be an even demand for resources over the entire project duration,
          with a smooth increase at the beginning of a project and a smooth decrease at the end. Given the
          limited nature of resources, thoughtful consideration should be given to the project resource
          requirements; the project plan should be refined when necessary so that it is practical.



             Did u know?  What are the four stages?
             The process of refining the plan to effectively manage and schedule resources (sometimes
             referred to as resource modeling) comprises four major stages: resource definition, resource
             allocation,  resource  aggregation,  and  resource  leveling  (which  includes  resource
             smoothing).

          Resource Allocation

          Resource allocation, also called resource loading, is  concerned with  assigning the required
          number of those resources identified in the previous step to each activity identified in the plan.
          More than one type of resource may be attributed to a specific activity. For example, fixing the
          plates on a ship’s hull may require  10 fitters, 20 welders, 15 laborers and a certain type of
          welding machine. From a practical standpoint, resource allocation does not have to follow a
          constant pattern; some activities may initially require fewer resources but may require more of
          the same resources during the later stages of the project. At this stage, the impact of any resource
          allocation decision is not known and we cannot yet answer questions such as:

              Is lack of resources on this particular activity having an adverse effect on the duration of
               the whole project? Such an activity is more likely to be on the critical path.





                                           LOVELY PROFESSIONAL UNIVERSITY                                   215
   216   217   218   219   220   221   222   223   224   225   226