Page 125 - DCAP305_PRINCIPLES_OF_SOFTWARE_ENGINEERING
P. 125
Unit 5: Software Project Planning
In addition, SGS has ensured top quality during the construction process with the slip form Notes
technique, a construction method used for tall structures such as chimneys, water tanks and
storage bins that is becoming increasingly popular among leading construction companies,
due to the considerable reduction in time and cost it offers.
SGS has checked the twisting of the slip form with respect to tolerance limits, controlled the
Reinforced Concrete shell thickness and slump as per design requirements, and has ensured
that the proper inner and outer diameters, clean cover and steel lap joints are maintained. With
SGS’s help, the chimney construction projects have been performed in compliance with all
international and local regulations and quality standards. SGS is one of very few companies
with the requisite technical expertise and manpower to supervise chimney construction. As
a result of SGS’s competence and experience, the contract with Bygging India Ltd. is being
renewed annually, in accordance with the client’s requirements. Moreover, SGS operations
may be extended to other countries in which Bygging India Ltd. carries out its work.
Questions
1. Explain the quality assurance and quality control during construction of a project
2. Define the quality assurance and quality control for the construction of chimneys in India.
Self Assessment Questions
6. Objective of software project planning is to provide a …………. that enables the manager
to make reasonable estimates of resources, cost, and schedule.
(a) framework (b) setup
(c) program (d) None of these.
7. ………… central plan, which describes how the system will be developed.
(a) Quality Assurance Plan (b) Validation Plan
(c) Maintenance Plan (d) Software Development Plan
8. …………………………. defines how the system will be configured and installed.
(a) Validation Plan (b) Configuration Management Plan
(c) Quality Assurance (d) Software Development Plan
9. A software project is developed through ……………………
(a) development processes (b) programmer
(c) software processes (d) life cycle of software
10. A requirement specification describing the details of the project to be developed forms a
point of departure for the …………… process.
(a) life cycle (b) execution
(c) estimation (d) maintenance
11. The Advanced COCOMO model computes …………. as a function of program size and
a set of cost drivers weighted according to each phase of the software lifecycle.
(a) cost of the program (b) range of the program
(c) program (d) effort
LOVELY PROFESSIONAL UNIVERSITY 119