Unit 6: Effort Estimation




          they need in order to produce estimates; nevertheless, they need to come up with numbers. To  Notes
          deal with incomplete information, they must make assumptions about the work to be done. By
          making assumptions, team members can leave placeholders for information that can be corrected
          later, in order to make the estimate more accurate.
          For  the estimates  to  be  most effective, the assumptions must be  written down.  Important
          information is discovered during the discussion that the team will need to refer back to during
          the development process, and if that information is not written down, the team will have to
          have the discussion all over again. If an assumption turns out to be incorrect, the schedule will
          need to be adjusted; they will be able to point to the exact cause of the delay by showing that a
          documented assumption turned out to be incorrect. This will help the project manager explain
          any resulting schedule delay to others in the organization and avoid that source of delays in the
          future. The assumptions also provide a way to keep a record of team decisions, share those
          decisions with others, and find errors in their decisions.

          The team should hold a brainstorming session to try to identify as many assumptions as possible.
          The bigger the list of assumptions, the lower the overall risk for the project. A project manager
          may get better  results from this session by helping the team see how these assumptions can
          work to their benefit. Any software engineer who has had a bad experience with an estimate that
          has turned out to be inaccurate will appreciate the value of assumptions: they serve as a warning
          to the rest of the organization that the estimate is contingent on the assumptions being true. If
          even one of these assumptions turns out to be incorrect, the team cannot be “blamed” for the
          incorrect estimate that resulted.
          While identifying assumptions is a skill that improves with experience, there are a set of questions
          that can help a novice team member figure out what assumptions he or she needs to make in
          order to properly estimate the software. The project manager can use these questions to help
          lead the discussion to identify the assumptions:
              Are there project goals that are known to the team but not written in any documentation?
              Are there any concepts, terms, or definitions that need to be clarified?

              Are there standards that must be met but will be expensive to comply with?
              How will the development of this project differ from that of previous projects? Will there
               be new tasks added that were not performed previously?

              Are there technology and architecture decisions that have already been made?
              What changes are likely to occur elsewhere in the  organization that could cause this
               estimate to be inaccurate?

              Are there any issues that the team is known to disagree on that will affect the project?
          The last bullet point is especially important. If one team member believes that the project will
          go down one path while another team member believes the project will go down a different
          path, the estimates could vary significantly, depending on which team member is correct. For
          example, one team member may think that a certain off-the-shelf component should be used
          because that is cheaper than building it, while another team member may believe that they must
          build that component  themselves because they cannot locate one  for sale  which suits  their
          particular needs. Instead of reaching an impasse, the team can  make an assumption—either
          assume that they will buy the component, or assume that they will build it—which will enable
          them to move forward with the estimate. It should be easier to reach an agreement at this point
          because it is not the final decision. By writing down the assumption, the team keeps a record of
          the disagreement and leaves open the possibility that this will change in the future. The written
          assumption will be especially useful later while doing a risk assessment for  the project plan
          because there is a risk that the assumption is incorrect.