Page 71 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 71

Unit 3: Work Breakdown Structure




          3.1 Uses for the WBS                                                                  Notes

          The WBS has four uses:
          1.   Thought process tool: The manager and the project team use WBS as a thought process tool
               that  helps them to visualize exactly how the work  of the  project can  be defined  and
               managed effectively.
          2.   Architectural design tool: WBS can be used as a design tool as it is a picture of the work of
               the project that shows how the items of work are related to one another.
          3.   Planning tool:  In  the  planning  phase,  the WBS  gives  the  project  team  a  detailed
               representation of the project as a collection of activities that must be completed in order
               for  the project  to be completed. It is at  the lowest  activity level  of WBS  that we will
               estimate effort, elapsed time, and resource requirements; build a schedule of when the
               work will be completed; and estimate deliverable dates and project completion.
          4.   Project status reporting tool: The WBS is used as a structure for reporting project status.
               The project activities are consolidated (that is, rolled up) from the bottom as lower-level
               activities are completed. As work is completed, activities will be completed. Completion
               of lower-level activities  causes higher-level activities to  be partially complete. Some of
               these higher-level activities may represent significant progress whose completion will be
               milestone events in the course of the project.




              Task  The WBS defines milestone events that can be reported to senior management and
             to the customer. Analyze

          WBS and the Project Manager

          It is the project manager who decides on the architecture of the WBS  and the level of detail
          required. This detail is important because the project manager is accountable for the success of
          the project. The WBS must be defined so that the project manager can manage the project. Apart
          from any senior management requirements for  reporting or organizational requirements for
          documentation or process, the project manager is free to develop the WBS according to his or her
          needs and those of management.

          3.2 Generating the WBS

          The best way to generate the WBS is as part of the Joint Project Planning (JPP) session. One of two
          simple decomposition processes is used to identify the activities that must be performed from
          the beginning to the completion of the project. These activities are the lowest level of managed
          work for the project manager. At this point in the planning process, you should have completed
          the Project Overview Statement. You may have to go back and reconsider the POS as a result of
          further planning activities, but for now let’s assume the POS is complete. Our technique for
          generating the WBS will reduce even the most complex project to a set of clearly defined activities.
          The WBS will be the document that guides the remainder of the planning activities.
          Two approaches can be used to identify the project activities:
              The first is the top-down approach.
              The second is the bottom-up approach.






                                           LOVELY PROFESSIONAL UNIVERSITY                                   65
   66   67   68   69   70   71   72   73   74   75   76