Page 75 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 75

Unit 3: Work Breakdown Structure




          Deliverable                                                                           Notes

          The result of completing the work that makes up the activity is the production of a deliverable.
          The deliverable is a visible sign that the activity is complete. This sign could be an approving
          manager’s signature, a physical product or document, the authorization to proceed to the next
          activity, or some other sign of completion.

          Cost/Time Estimate

          Each activity should have an estimated time and cost of completion. Being able to do this at the
          lowest level of decomposition in the WBS allows you to aggregate to higher levels and estimate
          the total project cost and the completion date. By successively decomposing activities to finer
          levels of granularity, you are likely to encounter primitive activities that you have performed
          before. This experience at lower levels of definition gives you a  stronger base on which to
          estimate activity cost and duration for similar activities.

          Acceptable Duration Limits

          While there is no fixed rule for the duration of an activity, it is recommended that activities should
          have a duration of less than two calendar weeks. This seems to be a common practice in many
          organizations. Even for long projects where contractors may be responsible for major pieces of
          work, they will generate plans that decompose their work to activities having this activity duration.

          Activity Independence

          It is important that each activity be independent. Once work has begun on the activity, it can
          continue reasonably without interruption and without the need of additional input or information
          until  the activity is complete. The work effort could be contiguous, but it  can be scheduled
          otherwise for a variety of reasons.




             Notes  You can choose to schedule it in parts because of resource availability, but  you
             could have scheduled it as one continuous stream of work.

          3.4 Using a Joint Project Planning Session to Build the WBS


          The best way to build a WBS is as a group activity. To create the WBS, assemble a facilitator, the
          project manager, the core members of the project team, and all other managers who might be
          affected by the project or who will affect the project. The important thing is to have the expertise
          and the decision makers present in this part of the planning session who can give input into the
          WBS. This exercise should be continuous. The steps to build WBS are as follows:
              The first step is for the whole planning team to decide on the first-level decomposition of
               the goal statement. One obvious approach would be to use the objective statements from
               the POS as the first-level decomposition.
              Once the first-level decomposition is developed, the  team has two choices on how to
               proceed:

                   Without a doubt, the best way (from a WBS completion point of view) is to have the
                    entire planning team remain intact and complete the WBS together. Often that will
                    not work simply from the standpoint of it taking more of everybody’s time and also
                    tying up the time of several high-level managers more than in the second choice.



                                           LOVELY PROFESSIONAL UNIVERSITY                                   69
   70   71   72   73   74   75   76   77   78   79   80