Page 296 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 296

Unit 14: Operations Scheduling




                                                                                                Notes
                           Table  14.5: Scheduling  Parameters for  our  Example  (2)
                            LCFS             Random              STR
                      Sequ-  Flow   Tardi-  Sequ-  Flow   Tardi-   Sequ-  Flow   Tardi-
                      ence   Time   ness   ence   Time   ness   ence   Time   ness
                      P5      4     0    P3     5     0     P5    4     0
                      P4     11     1    P1     8     2     P1    7     0
                      P3     16     3    P4    15     5     P4    14    6
                      P2     19    11    P5    19    11     P3    19    11
                      P1     22    16    P2    22    16     P2    22    16
                             72    31          69    34           66    33

          Table below is a comparison of the different scheduling procedures which we have considered
          above. It will be seen that no other sequence can produce  a better mean flow time than the
          sequence obtained by the SPT rule.  Also, the ‘average tardiness’ is the lowest using the STP
          procedure.  The optimality of the SPT rule can be  mathematically proved.  By finishing the
          shorter jobs first, both the turnaround time and the work-in-process inventory are reduced. The
          SPT procedure is simple to implement and provides good results even in the more complex
          scheduling situations.

                             Table  14.6: Comparison  of Scheduling  Procedures

                            Scheduling   Makespan    Mean Flow   Average
                            Rule         (days)   Time (days)   Tardiness
                            FCFS           60        12.0      29/5
                            STP            56        11.2      19/5
                            D – Date       58        11.6      22/5
                            LCFS           72        14.4      31/5
                            Random         69        13.8      34/5
                            STR            66        13.2      33/5

          However, STP could  increase total inventory value because it tends to push all  work to the
          finished state. It also tends to produce a large variance in past due hours because the larger jobs
          might have to wait a long time for processing. As it provides no opportunity to adjust schedules
          when due dates change, the advantage of this procedure over others diminishes as the load on
          the shop increases.

          Self Assessment

          Fill in the blanks:

          10.  ……………… constraints say that some tasks have to be  finished before others can  be
               started.
          11.  ……………… constraints say that two tasks requiring the same resource cannot be done
               simultaneously.
          12.  A schedule obtained by sequencing jobs in increasing order of processing times is called
               a ……………… rule.




                                           LOVELY PROFESSIONAL UNIVERSITY                                   291
   291   292   293   294   295   296   297   298   299   300