Unit 7: Budgeting





          The production manager consults the storekeeper and casts his figures as follows:      Notes
          Two kinds of raw materials A and B are required for manufacturing the product. Each unit
          of the product requires 2 units of A and 3 units of B. The estimated opening balances at the
          commencement of the next year are:

          Finished product   : 10,000 units
          Raw Materials A   : 12,000 units    Raw Materials B : 15,000 units
          The desirable closing balances at the end of the next year are:
          Finished products   : 14,000 units

          Raw materials A   : 13,000 units    Raw materials B : 1,000 units
          Prepare production budget and materials purchase budget for the next year.
          Solution:

          The first step is to prepare the production budget. To identify the volume of materials required
          for production by considering the production budget and the closing stock of materials of A and
          B respectively.
          Why the closing stock of raw materials has to be added with estimated consumption? The
          purpose of adding the closing stock of raw materials is to anticipate the future demand of them,
          due to market influence; which warrants the firm to go for placement of order not only taking


          into consideration of expected consumption of raw materials but also the closing stock of raw
          materials to be maintained at the end of the season, in order to facilitate to have uninterrupted
          flow of production.

          Why the opening stock of raw materials has to be deducted?
          The opening stock of raw materials, which is available in the firm, should be considered for the

          placement of order of raw materials. The materials to be ordered should be other than that of the
          materials available in the fi rm.

                                       Production Budget (Units)
           Estimated sales                                                    50,000
           Add: Desired Closing stock                                         14,000
                                                                              64,000
           Less: Opening Stock                                                10,000
           Estimated Production                                               54,000

                              Materials Procurement or Purchase Budget (Units)

                                            Material A                Material B
           Estimated Consumption
           For A 2 units × 54, 000           1,08,000
           For B 3 units × 54,000                                      1,62,000
           Add: Closing Stock                  13,000                   16,000
                                             1,21,000                  1,78,000
           Less: Opening Stock                 12,000                   15,000
           Estimated Purchases               1,09,000                  1,63,000