Page 240 - DCOM303_DMGT504_OPERATION_RESEARCH
P. 240

Unit 12: Critical Path Method and PERT




          2.   Looping error should not be formed in a network, as it represents performance of activities  Notes
               repeatedly in a cyclic manner, as shown below in Figure 12.7.

                                      Figure  12.7: Looping  Error


                                                         3




                                       1                 2

                                             Incorrect
          3.   In a network, there should be only one start event and one ending event as shown below,
               in Figure 12.8.

                                Figure  12.8: Only  One Start  and End  Event


                                                2




                      Start event  1                           4   End event



                                                3


          4.   The direction of arrows should flow from left  to right avoiding mixing of direction as
               shown in Figure 12.9.

                                Figure  12.9: Wrong  Direction of  Arrows


                                                      4


                  1            2           3                     6           7



                                                      5

                                                                     Incorrect

          Self Assessment

          Give one word for the following:
          1.   The shortest time taken to complete an activity.
          2.   The technique in which the time estimates are assumed to be known with certainty.
          3.   An imaginary activity that does not consume any resource and time
          4.   Activities that must be used only if it is necessary to reduce the complexity of the network.




                                           LOVELY PROFESSIONAL UNIVERSITY                                   235