Page 34 - DCOM404_CORPORATE_LEGAL_FRAMEWORK
P. 34

Unit 1: Laws of Contract




                                                                                                Notes
                 Examples:


          1.   A, a builder, contracts to erect and finish a house by the first of January, in order that B may
               give possession of it at that time to C, to whom B has contracted to let it. A is informed of
               the contract between B and C. A builds the house so badly that before the 1st of January
               it falls down and had to be rebuilt by B, who in consequence loses the rent which he was
               to have received from C, and is obliged to make compensation to C for the breach of his
               contract. A must make compensation to B for the cost of rebuilding the house, for the rent
               lost and for the compensation made to C.
          2.   A delivers to B, a common carrier, a machine to be conveyed without delay to A’s mill,
               informing B that his mill is stopped for want of the machine. B unreasonably delays
               the delivery of the machine and A, in consequence, loses a profitable contract with the

               government. A is entitled to receive from B, by way of compensation, the average amount

               of profit which would have been made by the working of the mill during the time that
               delivery of it was delayed. But, however, the loss sustained through the loss of the
               government contract cannot be claimed.
          3.   X’s mill was stopped due to the breakdown of a shaft. He delivered the shaft to Y, a
               common carrier, to be taken to a manufacturer to copy it and make a new one. X did not
               make known to Y that delay would result in a loss of profits. By some neglect on the part of

               Y the delivery of the shaft was delayed in transit beyond a reasonable time. As a result, the
               mill remained idle for a longer time than otherwise would have been, had the shaft been
               delivered in time? Held, Y was not liable for loss of profi ts during the period of delay as
               the circumstances communicated to Y did not show that a delay in the delivery of the shaft
               would entail loss of profits to the mill.

          4.   Where A contracts to sell and deliver to B on the 1st of January certain cloth which B
               intends to manufacture into caps of a particular kind for which there is no demand except
               in that season. The cloth is not delivered till after the appointed time and too late to be
               used that year in making caps. B is entitled to receive from A only ordinary damages, i.e.,
               the difference between the contract price of the cloth and its market price at the time of

               delivery but not the profits which he expected to obtain by making caps, nor the expenses
               which he has incurred in making preparation for the manufacture of caps.
          Whether Payment of Interest at a Higher Rate Amounts to Penalty?

          Whether an agreement to pay interest at a higher rate in the case of breach of a contract amounts
          to penalty shall depend upon the circumstances of each case However, following rules may be
          helpful in understanding the legal position in this regard.
          (i)   A stipulation for increased interest from the date of default shall be a stipulation by way
               of penalty if the rate of interest is abnormally high. A gives B a bond for the repayment of
               ` 1,000 with interest at 12% p.a. at the end of six months with a stipulation that in case of
               default interest shall be payable at the rate of 75 per cent from the date of default. This is a
               stipulation by way of penalty and B is only entitled to recover from A such compensation
               as the court considers reasonable.
          (ii)   Where there is a stipulation to pay increased interest from the date of the bond and not
               merely from the date of default; it is always to be considered as penalty.
          (iii)  As regards compound interest, it is not itself a penalty. But it is allowed only in cases
               where the parties expressly agree to it. However a stipulation to pay compound interest at
               a higher rate on default is considered as a penalty.
          (iv)  An agreement to pay a particular rate of interest with stipulation that a reduced rate will
               be acceptable if paid punctually is not a stipulation by way of penalty. Thus, where a bond




                                           LOVELY PROFESSIONAL UNIVERSITY                                    29
   29   30   31   32   33   34   35   36   37   38   39