                    notes          3.   Industry  –  specific  experience  (knowledge  of  the  various  industry  –  specific  business
                                       processes)
                                   4.   Finances involved in hiring the particular consultant

                                   implementation of the erp package

                                   The broad steps involved in the implementation of the ERP package are:
                                   1.   Formation of implementation team
                                   2.   Preparation of implementation plan
                                   3.   Mapping of business processes on to the package

                                   4.   Gap analysis
                                   5.   Customization
                                   6.   Development of user – specific reports and transactions
                                   7.   Uploading of data from existing systems
                                   8.   Test runs

                                   9.   User training
                                   10.   Parallel run
                                   11.   Concurrence from user on satisfactory working of the system
                                   12.   Migration to the new system

                                   13.   User documentation
                                   14.   Post-implementation support
                                   15.   System monitoring and fine tuning

                                   Formation of Implementation Team

                                   It is of the greatest importance to form an implementation team consisting of knowledgeable users
                                   from all functions along with IT personnel and personnel from the implementation consultant.
                                   From the people chosen, the project manager, project leaders and the module leaders should
                                   be  identified  and  also  a  steering  committee  should  be  formed.  The  functions  of  the  steering
                                   committee are:
                                   1.   To monitor the progress of the implementation
                                   2.   To see to it that the schedule of the implementation is adhered to
                                   3.   Resolve any problems that come up in the due course of the implementation

                                   4.   Allocation of resources for implementation

                                   Preparation of Implementation Plan

                                   An important task is the preparation of a detailed implementation plan that covers the total
                                   implementation process. Here various project management techniques like PERT charts can be
                                   used. The implementation plan should have clear components and should include the schedule
                                   for the following:
                                   1.   Training of the project team

                                   2.   Mapping of business processes onto the software


          150                              LoveLy professionaL university