                    Notes             Range of Application: By differentiating the estimation equations according to project
                                       sizes and system types, the range of application for method COCOMO is a wide one. It is
                                       also one of the few estimation methods offering-apart from the support for development
                                       projects-support for  the effort estimation of  SWMM tasks as well (also by  parametric
                                       estimation equations) as for the estimation of the project duration.
                                      Tool Support:  Computer-based support  is  required  for  Intermediate and  Detailed
                                       COCOMO, based on the quantity problem (differentiation of influence factors on phases
                                       and sub products.

                                   6.7.4 Modes

                                   COCOMO can be applied to the following software project’s categories.

                                   Organic Mode

                                   These projects are very easy and have small team size. The team has a good application experience
                                   work to a set of less than inflexible/rigid requirements. A thermal analysis program developed
                                   for a heat transfer group is an example of this.

                                   Semi-detached Mode

                                   These are intermediate in size and complexity. Here the team has mixed experience to meet up
                                   a mix of rigid and less than rigid requirements. A  transaction processing system with fixed
                                   requirements for terminal hardware and database software is an example of this.

                                   Embedded Mode

                                   Software projects that must be developed within a set of tight hardware, software, and operational
                                   constraints. For example, flight control software for aircraft.


                                   Self Assessment

                                   Fill in the blanks:
                                   13.  The …………………..  Method were defined by Charles Symons in book published in 1991.
                                   14.  Basic …………………….. is static single-valued model that computes software development
                                       effort (and cost) as a function of program size expressed in estimated lines of code.
                                   15.  The micro estimation allows the effort allocation to activities and…………………………..

                                     


                                     Caselet    Nasscom Reiterates 16-18% Growth Estimate in IT Sector

                                     Thiruvananthapuram Sept. 30:
                                     The National Association of Software and Service Companies has stuck to its 16-18 per
                                     cent annual growth estimate in the IT sector and termed the outlook positive.
                                     Speaking to newspersons here after the Executive Council met in Kerala for the first time,
                                     the Nasscom Chairman, Mr Rajendra Pawar, and the President, Mr Som Mittal, announced
                                     the setting up of a regional chapter in the State.
                                                                                                        Contd.....


          136                               LOVELY PROFESSIONAL UNIVERSITY
   137   138   139   140   141   142   143   144   145   146   147