Unit 12: Monitoring & Control




          12.5 Purpose of Controls                                                              Notes

          Controls are actions taken as a result of reports. When implemented, controls are designed to
          bring actual project status back into conformance with the project plan. These reports are designed
          to support control activities by drawing attention to certain aspects or characteristics of the
          project, such as planned versus actual schedule, trends in the schedule, and actual versus planned
          resource use.
          We typically track performance levels, costs, and time schedules. There are three reasons to use
          reports in your project.
          1.   To track progress: The project manager will want to use a periodic (at least biweekly, but
               weekly is best) reporting system that identifies the status of every activity scheduled for
               work since  the last progress report. These reports summarize progress for the current
               period as well as the cumulative progress for the entire project.
          2.   To detect variance from plan: Variance reports are of particular importance to management.
               They are  simple and intuitive, and they give  managers an  excellent tool  by which to
               quickly assess the health of a project. To detect variance, the project manager needs to
               compare planned performance to actual performance.
          3.   To take corrective action: To take corrective  action, it is necessary to know where  the
               problem is and to have that information in time to do something about it. Once there is a
               significant variance from plan, the next step is to determine whether corrective action is
               needed and then act appropriately.

          12.6 Balancing the Control System


                               Figure 12.7:  The Total Cost of  Control and  Risk























          It is very easy to get carried away with controls and reports. The more controls that are put in place,
          the lower the project risk, and the less likely it will be for the project to get in trouble. As figure 12.7
          shows, however, there is a point of diminishing returns. Cost aside, there is another impact to
          consider. To comply with the project controls, project team members will have to spend time
          preparing and defending progress reports. This subtracts from the time spent doing project work.
          The project manager needs to strike a balance between the extent of the control system and the
          risk of unfavorable outcomes.  Figure 12.7 shows the  relationship between risk and control.
          Conceptually, there is a balance point that minimizes the total cost exposure for having chosen
          a particular level of control.