Software Project Management




                    Notes          Positive variances bring their own set of problems, which can be as serious as negative variances.
                                   Positive variances can allow for rescheduling to bring the project to completion early, under
                                   budget, or both. Resources can be reallocated from ahead-of-schedule projects to behind-schedule
                                   projects.

                                   Negative Variances

                                   Negative variances are deviations from plan that indicate that a behind-schedule situation has
                                   occurred or that an actual cost was greater than a planned cost.
                                   Negative variances, just like positive variances, are not necessarily bad news. For example, you
                                   might have overspent because you accomplished more work during the report period than was
                                   planned. But in overspending during this period, you could have accomplished the work at less
                                   cost than was originally planned. You can’t tell by looking at the variance report.

                                   In most cases, negative time variances affect project completion only if they are associated with
                                   critical  path activities or if the schedule slippage on non-critical path activities exceeds  the
                                   activity’s total float. Variances use up the float time for that  activity; more serious ones will
                                   cause a change in the critical path.
                                   Negative cost variances can result from uncontrollable factors such as cost increases from suppliers
                                   or unexpected equipment malfunctions. Some negative variances can result from inefficiencies
                                   or error.

                                   12.8 Graphical Reporting Tools


                                   Usually senior managers have only a few minutes of uninterrupted time to digest your report.
                                   Having to read several pages only to find out that the project is on schedule is frustrating and a
                                   waste of valuable time. For this it is better to present them the report in the form of graphics.
                                   You can use the Gantt charts (See Figure 12.8) and Milestone Trend Charts (See Figure 12.9) for
                                   this purpose.
                                                            Figure  12.8: A  Typical  Gantt  Chart