Page 72 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 72

Software Project Management




                    Notes          3.2.1 Top-down Approach

                                   The top-down approach begins  at the  goal level and successively partitions work down to
                                   lower levels of definition until the participants are satisfied that the work has been sufficiently
                                   defined.
                                   Once the project activities have been defined using the top-down approach, they will be defined
                                   at a sufficient level of detail to allow you to estimate time, cost, and resource requirements first
                                   at the activity level and then aggregate to the project level.

                                       !

                                     Caution  Because the activities are defined to this level of detail, project time, cost, and
                                     resource requirements are estimated much more accurately.
                                   Once the activities are described, you can sequence the project work so that as many activities as
                                   possible are performed in parallel, rather than in sequence.
                                   There are two variations of the top-down approach:
                                      Team approach

                                      Sub-team approach

                                   Team Approach

                                   In this approach the entire team works on all parts of the WBS. For each Level 1 activity, appoint
                                   the most knowledgeable member of the planning team to facilitate the further decomposition
                                   of that part of the WBS. Continue with similar appointments until the WBS is complete. This
                                   approach allows all members of the planning team to pay particular attention to the WBS as it is
                                   developed, noting discrepancies and commenting on them in real time.
                                   The team approach is better then the sub-team approach but it requires more time to complete.

                                   Sub-team Approach

                                   When time is at a premium, the planning facilitator will prefer the sub-team approach. The first
                                   step is to divide the planning team into as many sub-teams as there are activities at Level 1 of the
                                   WBS. Then follow these steps:
                                   1.  The planning team agrees on the approach to building the first level of the Work Breakdown
                                       Structure.
                                   2.  The planning team creates the Level 1 activities.
                                   3.  A subject matter expert leads the team in further decomposition of the WBS for his or her
                                       area of expertise.
                                   4.  The team suggests decomposition ideas for the expert until each activity within the Level
                                       1 activities meets the WBS completion criteria.



                                     Did u know?  What is decomposition?

                                     Decomposition (or rotting) is the process by which organic material is broken down into
                                     simpler forms of matter.






          66                                LOVELY PROFESSIONAL UNIVERSITY
   67   68   69   70   71   72   73   74   75   76   77