Unit 7: Variance Analysis




          Due to shortage of material, it was decided to reduce the consumption of A by 15% and increase   Notes
          that of material B by 30%.
          The above problem does not have any difference in between the total actual quantity and standard
          quantity of materials. In both the cases the total quantity of materials are equivalent to 300 units.
          If both are equivalent to each other, the standard mix would be the revised standard mix of the
          materials.

          Solution:
          Revised Standard Mix:
                    200
          Material A    = × 300 Units = 200 units
                    300
                     100
          Material B =    × 300 Units = 100 units
                     300

          After finding out the revised standard mix of the materials, the changes on the consumption should
          be incorporated due to the shortage of materials to the tune of actual quantity of materials.
          For material A, there is reduction in the actual consumption in the quantity of materials amounted
          15%.
          For material B, there is spurt increase in the consumption of material B due to fill up the shortage

          of material A i.e 30% increase on material B.
          Final Revised standard Mix of Material   A : 200 units – 15% of 200 units = 170 units
                                               B : 100 units + 30% of 100 units = 130 units
          Material Mix Variance
          Material Mix Variance = Standard Price (Revised Standard Quantity – Actual Quantity)

          MMV Material A = ` 12 (170 units – 160 units)  = ` 120 Favourable
          MMV Material B = ` 10 (130 units – 140 units)  = ` 100 Adverse
          Total Material Mix Variance           = ` 20 Favourable




             Notes
              The material mix variance is one of the components of material usage variance.

          Material Sub-usage Variance

          This is the variance in between standard quantity and revised standard quantity of materials
          denominated in terms of standard price. The purpose of studying the difference in between
          these two is to analyse the amount of deviation of the standard against the revised standard in
          line with the actual fluctuation in the quantity of materials consumption during the production

          process. It is the only variance highlights the difference in between the early set standard and the
          redesigned standard in terms of actual quantity of materials for meaningful comparison.
          Material Sub-usage Variance = Standard Cost per unit (Standard Quantity – Revised Standard
          Quantity).
          If the total actual quantity of materials consumption in units is equivalent to the total standard
          quantity of materials, nullifies the material sub-usage variance in between the standard quantity

          of materials and revised standard quantity of materials. It means that the standard quantity of