                                          Example:
                                   Time Allowed          20 hours
                                   Time Saved            4 hours

                                   Hourly Rate           ` 5 per hour
                                   Calculate total earnings under:
                                   1.  Halsey and
                                   2.  Rowan Plan
                                   Solution:

                                   Time taken is not given. Hence, it is to be ascertained.
                                   Time Allowed                                              =  20 hours
                                   Less: Time Saved,                                         =  4 hours
                                   Time taken                                                =  16 hours
                                   Total earnings under Halsey Plan:
                                   Normal wages = TT × HR=16 × 5                             =  ` 80
                                   Bonus 1/2 × TS × HR = 1/2 × 4 × 5                         =  ` 10
                                   Total earnings                                            =  ` 90
                                   Total earnings under Rowan Plan:
                                   Normal wages = TT × HR = 16 × 5                           =  ` 80
                                   Bonus TS/TA × NW – 4/20 × 80                              =  ` 16
                                   Total earnings                                            =  ` 96


                                          Example: From the following particulars, work out the earnings for the week of a worker
                                   under:
                                   1.   Straight Piece Rate

                                   2.   Differential Piece Rate
                                   3.   Halsey Premium System
                                   4.  Rowan System
                                       Number of working hours per week    - 48

                                       Wages per hour                  - ` 3.75
                                       Normal time per piece           - 20 minutes
                                       Normal output per week          - 120 Pieces
                                       Actual output for the week      - 150 Pieces
                                       Differential piece rate         - 80% of piece rate

                                       When output is below standard and 12% when above standard.
                                   Solution:
                                   Weekly wages 48 × 3.75 = ` 180.00
                                   Rate per unit = 180/120 = ` 1.50