                    Notes          Solution:
                                   First step is to find out the standard quantity for actual output
                                   Standard quantity of raw materials = 2Kg
                                   Actual Production = 400 units

                                   To have leveled comparison, the Standard quantity of materials for actual output to computed;
                                   then only the variance intend to encircle will be meaningful or vice-versa.
                                   The computation of SQAO should be computed at first:

                                   For the production of one unit of product 2 Kg of raw material was planned and finalized prior
                                   to the commencement of production process. The actual production of the firm during the cycle
                                   is 400 units. What would be the requirement of the firm in manufacturing 400 units to the tune
                                   of planned quantity of materials per unit 2 Kg? This is the standard quantity of materials for
                                   actual output  computed for an effective  comparison  with the actual  quantity of materials
                                   consumed by the firm in manufacturing the 400 units.
                                                                  SQAO = 400 × 2Kg = 800 Kg

                                                       SP = Standard Price =  2 per Kg
                                                     AQ = Actual Quantity = 850 Kgs
                                                        AP = Actual Price =  1.80
                                                    Material Cost Variance = (SQAO × SP) – (AQ × AP)

                                                                        = (800 Kg × 2) – (850 Kg × 1.8)
                                                                        =  1600 – 1530
                                                                        =  70 (F)
                                   The material cost variance of the above problem is favourable due to lesser actual cost over the
                                   standard cost of materials.

                                   11.2.2 Material Price Variance

                                   It is very simple to understand that the name of the variance is self-explanatory in explaining the
                                   meaning of the variance. It is a variance in between two different prices viz. the standard price
                                   and actual price of raw materials. The difference should be expressed only in terms of the actual
                                   usage of materials. The ultimate of aim of expressing this variance in the lights of actual usage
                                   of materials is to identify the deviation of the price changes in line with the purchase of raw
                                   materials.
                                                    Material Price Variance = (SP – AP) AQ
                                   From the earlier illustration, the material price variance is as follows
                                                           Standard price =   2 per unit
                                                             Actual price =   1.80 per unit

                                       Actual quantity of materials consumed = 850 Kg
                                                    Material price variance = 850 Kg (2.00 – 1.80)
                                                    Material price variance =  170 (F)

                                   Decision criterion:  If the resultant is  positive, it  means that  the planned  price which  was
                                   scientifically developed is more than the actual price. In precise terms, the price fluctuations in