Unit 14: Conflict and Negotiation




             PERT Network – Activity on Node (AON)                                              Notes

































             Variance Calculation






















             PERT Formulae: Variance & Standard Deviation

                 b a  2
                   
             v      
                 6  
                          v
              (sum total of  of activitios on CP)
             What-if Analysis
             Since  PERT recognizes uncertainty in estimates of durations, it  gives rough  estimates
             about final completion. Now what-if analysis can be conducted like what is the probability

                                                                                 Contd...