Unit 8: Network Planning Model




          line so that they  are worked  on concurrently with other  activities. The  sequencing is often  Notes
          driven more by resource availability than any other consideration.
          There are two drawbacks to using the Gantt chart:

              Because of its simplicity, the Gantt chart does not contain detailed information. It reflects
               only the order imposed by the manager and, in fact,  hides much  of that information.
               Unless you are intimately familiar with the project activities, you cannot tell from the
               Gantt chart what must come before and after what.
              Second, the Gantt chart does not tell the project manager whether the schedule that results
               from the Gantt chart completes the project in the shortest possible time or even uses the
               resources most effectively.




              Task  The Gantt chart reflects only when the manager would like to have the work done.
             Explain

          Network Diagram

          The network diagram provides a visual layout of the sequence in which project work flows.
          It includes detailed information and serves as an analytical tool for project scheduling  and
          resource management  problems as they arise during the life of the project.  In addition, the
          network diagram allows you to compute the earliest time at which the project can be completed.
          That information does not follow from a Gantt chart.
          Network diagrams can be used for detailed project planning, during implementation as a tool
          for analyzing scheduling alternatives, and as a control tool:
          Planning: Even for large projects, the Network Planning Model gives a clear graphical picture of
          the relationship between project activities. It is, at the same time, a high-level and detailed-level
          view of the project.

          Implementation: For those project managers who use automated project management software
          tools, you will update the project file with activity status and estimate-to-completion data. The
          network diagram is then automatically updated and can be printed or viewed.

          Control: While the updated network diagram retains the status of all activities, the best graphical
          report for monitoring and controlling project work will be the Gantt chart view of the network
          diagram. This Gantt chart cannot be used for control purposes unless you have done network
          scheduling or incorporated the logic into the Gantt chart.




             Notes  Comparing the planned schedule with the actual schedule, the project manager will
             discover variances and, depending on their severity, will be able to put a get-well plan in
             place.

          Self Assessment

          Fill in the blanks:
          1.   A ……………………. is a pictorial representation of the sequence in which the project
               work can be done.
          2.   The …………………… is the older of the two and is  used effectively  in simple,  short-
               duration types of projects.