Page 163 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 163

Unit 8: Network Planning Model




          Latest Start Time (LS) and Latest Finish Time (LF)                                    Notes

          The latest start (LS) and latest finish (LF) times of an activity are the latest times at which the
          activity can start or finish without causing a delay in the completion of the project. Knowing
          these times is valuable for the project manager, who must make decisions on resource scheduling
          that can affect completion dates. The steps are as follows:

              The window of time between the ES and LF of an activity is the window within which the
               resource for the work must be scheduled or the project completion date will be delayed.
              To calculate these times, you work backward in the network diagram. First set the LF time
               of the last activity on the network to its calculated EF time. Its LS is calculated as [(LF –
               Duration) + One time unit]. Again, you add the one time unit to adjust for the start and
               finish of an activity within the same day.
              The LF time of all immediate predecessor activities is determined by the minimum of the
               LS, minus one time unit, times of all activities for which it is the predecessor.

          For  example, let’s calculate the late schedule for activity E in  Figure 8.7. Its only  successor,
          activity F, has an LS date of day 10. The LF date for its only predecessor, activity E, will therefore
          be the end of day 9. In other words, activity E must finish no later than the end of day 9 or it will
          delay the start of activity F and hence delay the completion date of the project. The LS date for
          activity E will be, using the formula, 9 – 2 + 1, or the beginning of day 7. On the other hand,
          consider activity C. It has two successor activities, activity D and activity E. The LS dates for them
          are day 5 and day 7, respectively. The minimum of those dates, day 5, is used to calculate the LF
          of activity C, namely, the end of day 4.

                                  Figure 8.7:  Backward  Pass  Calculations















          Calculating Critical Path

          As mentioned, the critical path is the longest path or sequence of activities (in terms of activity
          duration) through the network diagram. The critical path for the example problem we used to
          calculate the early schedule and the late schedule is shown in Figure 8.8.

                                       Figure  8.8: Critical  Path

















                                           LOVELY PROFESSIONAL UNIVERSITY                                   157
   158   159   160   161   162   163   164   165   166   167   168