Unit 12: Critical Path Method and PERT




               Activity:    A    B    C   D    E    F    G    H    I    J   K                   Notes
               Time  (days):  9  6    2    7   10   3    6    1    7    2   5
               The predecessor activities are given below:
                              Activity                         Predecessor
                                A                                  -
                                B                                  -
                                C                                  A
                                D                                  A
                                E                                  C
                                F                                  B
                                G                                 E,F
                                H                                  D
                                I                                 H,E
                                J                                  I
                                K                                  G

          10.  Draw the network from the following activity and find the critical path and total duration
               of project.

                             Activity                        Duration (days)
                               1-2                                5
                               1-3                                3
                               1-4                                6
                               2-3                                8
                               2-5                                7
                               3-5                                2
                               4-5                                6

          11.  Draw a network diagram and determine the project duration.
                               Activity                        Duration (weeks)
                                 1-2                                 2
                                 1-4                                 4
                                 1-3                                 7
                                 2-5                                 6
                              3-4 (Dummy)                            0
                                 4-6                                 6
                                 3-6                                 8
                                 5-7                                10
                                 5-6                                 9
                                 5-8                                 2
                                 6-7                                 6
                                 7-9                                 2
                                 8-9                                 5