Page 246 - DCOM303_DMGT504_OPERATION_RESEARCH
P. 246

Unit 12: Critical Path Method and PERT




          Total float TF : The total float of an activity is the difference between the latest start time and the  Notes
                     ij
          earliest start time of that activity.
                                  TF = LS  – ES                                     (1)
                                    ij    ij  ij
                                    or
                                  TF = (T  – T ) – t                                (2)
                                    ij   L  E   ij
          Free Float FF : The time by which the completion of an activity can be delayed from its earliest
                     ij
          finish time without affecting the earliest start time of the succeeding activity is called free float.
                                 FF  = (E – E ) – t                                 (3)
                                    ij   j   i  ij
                                  FF  = Total float – Head event slack
                                    ij
          Independent Float IF : The amount of time by which the start of an activity can be delayed
                           ij
          without affecting the earliest start time of any immediately following activities, assuming that
          the preceding activity has finished at its latest finish time.

                                  IF  = (E – L ) – t                                (4)
                                    ij   j   i  ij
                                  IF  = Free float – Tail event slack
                                    ij
                  Where tail event slack = L-E
                                        i  i

               !
             Caution  The negative value of independent float is considered to be zero.
          Critical Path: After determining the earliest and the latest scheduled times for various activities,
          the minimum time required to complete the project is calculated. In a network, among various
          paths, the longest path which determines the total time duration of the project is called the
          critical path. The following conditions must be satisfied in locating the critical path of a network.

          An activity is said to be critical only if both the conditions are satisfied.
          1.   T  – T  = 0
                L  E
          2.   T  – t  – T  = 0
                Lj  ij  Ej

                Example: A project schedule has the following characteristics as shown in Table 12.4

                                     Table  12.4:  Project  Schedule

                Activity     Name      Time      Activity   Name        Time (days)
                  1-2         A          4        5-6         G             4
                  1-3         B          1        5-7         H             8
                  2-4         C          1        6-8         I             1
                  3-4         D          1        7-8         J             2
                  3-5         E          6        8-10        K             5
                  4-9          F         5        9-10        L             7

          1.   Construct a network diagram.
          2.   Compute T  and T  for each activity.
                        E     L
          3.   Find the critical path.





                                           LOVELY PROFESSIONAL UNIVERSITY                                   241
   241   242   243   244   245   246   247   248   249   250   251