Notes Taking all these time estimates into consideration, the expected time of an activity is arrived at.
The average or mean (t ) value of the activity duration is given by,
a
(5)
The variance of the activity time is calculated using the formula,
(6)
Probability for Project Duration
The probability of completing the project within the scheduled time (T ) or contracted time may
s
be obtained by using the standard normal deviate where T is the expected time of project
e
completion.
(7)
Probability of completing the project within the scheduled time is,
P (T< T ) = P ( Z< Z ) (from normal tables) (8)
s 0
Example: An R&D project has a list of tasks to be performed whose time estimates are
given in the Table 12.8, as follows.
Time expected for each activity is calculated using the formula (5):
T =
a
= = = 6 days for activity A
Similarly, the expected time is calculated for all the activities.
The variance of activity time is calculated using the formula (6).
=
= = 0.444
Similarly, variances of all the activities are calculated. Construct a network diagram and calculate
the time earliest, T and time Latest T for all the activities.
E L