Page 253 - DCOM303_DMGT504_OPERATION_RESEARCH
P. 253

Operations Research




                    Notes          Solution:
                                   Calculate the time average t  and variances of each activity as shown in Table 12.9.
                                                         a
                                                                           2
                                                             Table 12.9:  T  &    Calculated
                                                                       e
                                        Activity       To          Tm          Tp          Ta          2
                                          1-2          4           6           8           6         0.444
                                          1-3          2           3           10          4         1.777
                                          1-4          6           8           16          9         2.777
                                          2-4          1           2           3           2         0.111
                                          3-4          6           7           8           7         0.111
                                          3-5          6           7           14          8         1.777
                                          4-6          3           5           7           5         0.444
                                          4-7          4           11          12         10         1.777
                                          5-7          2           4           6           4         0.444
                                          6-7          2           9           10          8         1.777

                                   From the network diagram Figure 12.19, the critical path is identified as 1-4, 4-6, 6-7, with a
                                   project duration of 22 days.
                                   The probability of completing the project within 19 days is given by, P(Z< Z )
                                                                                                0
                                   To find Z ,
                                          0
                                                               
                                                              
                                                            

                                                                 
                                           
                                                                  
                                                                
                                                
                                           
                                                  = -1.3416 days
                                                
                                   we know, P (Z <Z ) = 0.5 –   (1.3416) (from normal tables,  (1.3416) = 0.4099)
                                                 0
                                          = 0.5 – 0.4099
                                          = 0.0901
                                          = 9.01%
                                   Thus, the probability of completing the R&D project in 19 days is 9.01%. Since the probability of
                                   completing the project in 19 days is less than 20%, we find the probability of completing if in 24
                                   days.

                                             
                                               
                                                          
                                                 =           = 0.8944 days
                                                           