Operations Research
Notes It is more of an event-oriented technique rather than start- and completion-oriented, and
is used more in projects where time, rather than cost, is the major factor.
It is applied to very large-scale, one-time, complex, non-routine infrastructure and Research
and Development projects.
Program Evaluation and Review Technique (PERT) takes the CPM network and adds
distributions to represent the activity times of the project.
12.6 Keywords
Controlling: The process of analyzing and evaluating the actual progress against the plan.
Float: The amount of time available by which it is possible to delay its completion time without
extending the overall project completion time.
Planning: Process of creating and maintaining a plan.
Scheduling: The process of deciding how to commit resources between the varieties of possible
tasks.
Slack: The amount of time that a task in a project network can be delayed without causing a
delay to subsequent tasks and project completion date.
12.7 Review Questions
1. Prepare a network diagram for constructing a 5 floor apartment. The major activities of
the project are given as follows:
Activity Description Immediate Predecessor
A Selection of site -
B Preparation of drawings -
C Arranging the for finance A
D Selection of contractor A
E Getting approval from Govt A
F Laying the foundation E
G Start construction D, F
H Advertise in newspaper B, C
I Allocation of tenants G, H
2. For the problem No. 1 the time estimates in days are given. Determine the Time earliest
and Time latest, and the critical activities
Activity A B C D E F G H I
Time 3 5 7 2 5 20 60 2 10
(days)
3. An assembly having the following sequence of activities given along with their predecessor
in the table below. Draw a network diagram for the assembly.