Operations Research




                    Notes             It is more of an event-oriented technique rather than start- and completion-oriented, and
                                       is used more in projects where time, rather than cost, is the major factor.

                                      It is applied to very large-scale, one-time, complex, non-routine infrastructure and Research
                                       and Development projects.
                                      Program Evaluation and  Review Technique (PERT) takes the CPM network and  adds
                                       distributions to represent the activity times of the project.

                                   12.6 Keywords

                                   Controlling: The process of analyzing and evaluating the actual progress against the plan.
                                   Float: The amount of time available by which it is possible to delay its completion time without
                                   extending the overall project completion time.
                                   Planning: Process of creating and maintaining a plan.
                                   Scheduling: The process of deciding how to commit resources between the varieties of possible
                                   tasks.
                                   Slack: The amount of time that a task in a project network can be delayed without causing a
                                   delay to subsequent tasks and project completion date.

                                   12.7 Review Questions


                                   1.  Prepare a network diagram for constructing a 5 floor apartment. The major activities of
                                       the project are given as follows:

                                             Activity              Description            Immediate Predecessor
                                               A       Selection of site                          -
                                               B       Preparation of drawings                    -
                                               C       Arranging the for finance                  A
                                               D       Selection of contractor                    A
                                               E       Getting approval from Govt                 A
                                               F       Laying the foundation                      E
                                               G       Start construction                        D, F
                                               H       Advertise in newspaper                    B, C
                                               I       Allocation of tenants                     G, H

                                   2.  For the problem No. 1 the time estimates in days are given. Determine the Time earliest
                                       and Time latest, and the critical activities
                                          Activity   A    B     C     D     E      F      G      H        I
                                           Time     3     5     7     2     5      20    60      2       10
                                           (days)

                                   3.  An assembly having the following sequence of activities given along with their predecessor
                                       in the table below. Draw a network diagram for the assembly.