Unit 9: Variance Analysis




          Solution:                                                                             Notes


          First step is to find out the standard quantity for actual output
          Standard quantity of raw materials = 2Kg
          Actual Production = 400 units
          To have leveled comparison, the Standard quantity of materials for actual output to computed;
          then only the variance intend to encircle will be meaningful or vice versa.
          The computation of SQAO should be computed at fi rst:
          For the production of one unit of product 2 Kg of raw material was planned and fi nalized prior

          to the commencement of production process. The actual production of the firm during the cycle

          is 400 units. What would be the requirement of the firm in manufacturing 400 units to the tune of
          planned quantity of materials per unit 2 Kg? This is the standard quantity of materials for actual
          output computed for an effective comparison with the actual quantity of materials consumed by

          the firm in manufacturing the 400 units.
                                       SQAO = 400 × 2Kg = 800 Kg
                            SP = Standard Price = ` 2 per Kg
                          AQ = Actual Quantity = 850 Kgs
                              AP = Actual Price = ` 1.80
                          Material cost variance = (SQAO × SP) – (AQ × AP)

                                            = (800 Kg × ` 2) – (850 Kg × ` 1.8)
                                            = ` 1600 – ` 1530
                                            = ` 70 (F)
          The material cost variance of the above problem is favourable due to lesser actual cost over the
          standard cost of materials.

          Material Price Variance

          It is very simple to understand that the name of the variance is self-explanatory in explaining the
          meaning of the variance. It is a variance in between two different prices viz. the standard price and
          actual price of raw materials. The difference should be expressed only in terms of the actual usage
          of materials. The ultimate of aim of expressing this variance in the lights of actual usage of materials
          is to identify the deviation of the price changes in line with the purchase of raw materials.

                         Material Price Variance = (SP – AP) AQ
          From the earlier illustration, the material price variance is as follows
                                Standard price = ` 2 per unit
                                  Actual price = ` 1.80 per unit

             Actual quantity of materials consumed = 850 Kg
                          Material price variance = 850 Kg (2.00 – 1.80)
                                            = ` 170 (F)
          Decision Criterion:  If the resultant is positive, it means that the planned price which was
          scientifi cally developed is more than the actual price. In precise terms, the price fl uctuations in

          the market are well with in the planned price. If it is within the standard, quantified as favourable




                                           LOVELY PROFESSIONAL UNIVERSITY                                   165