                                        MCV = MPV + MUV                                         Notes

                                     ` 250 (A) = ` 2750 (F) + ` 3000 (A)
                                        L.H.S = R.H.S




              Task   If the closing stock of raw materials is given, how the material variance can be
             computed?
             Standard quantity of materials = 5000 Kgs @ ` 5 per Kg
             Actual quantity of materials purchased = 5500 Kgs @ ` 6 per Kg
             Closing stock of raw materials = 300 Kgs

          Material Mix Variance

          This kind of variance arises only due to the mixture of various raw materials to produce and to
          get an output. Normally the process of production involves more than two materials to get the

          output. For example the firm mixes the raw materials of A& B at the ratio of 3:2. The mixture is
          called Material Mix.
          The above mentioned ratio is being changed by the firm for actual production in producing a unit

          of product as 4:1.
          The change in the material mix due to various reasons, those are following:
          1.   In adequate supply of raw materials

          2.   Price factor of a material
          3.   Introduction of a new system of production due to expansion
          4.   Substitution of a material due better quality and cheaper price than the existing material in
               current system of procurement.
          This material mix variance is highly applicable in the following industries that chemicals,
          fertilizers, pharmaceuticals, consumables, etc.
          The variance should be computed in between two different materials viz. Standard quantity of
          materials and Actual quantity of materials.
          Actual quantity of materials is the volume of materials registered the change in the usage of raw
          materials mixture but the standard quantity of raw materials is totally free from the change of
          mixture in the raw materials.
          While studying the variance, the factors of comparison should be weighed equally with each
          other. For instance, the standard quantity of material should not be a rational factor of comparison
          with actual.

               !
             Caution  Why must the standard quantity of raw material be revised?
             In order to have an appropriate comparison, the standard has to be revised. The early
             estimated standard is the measure not considered the reality during the production
             process due to changes occurred in the procurement of raw materials. While comparing the
             standard with actual, the earlier is not at par with later in terms of realities. To incorporate
             the realities, the standards are tuned towards the actual; makes the comparison meaningful
             in studying the variance among the both.