Page 150 - DCAP601_SIMULATION_AND_MODELING
P. 150

Simulation and Modelling



                      Notes            2.  Which are the critical activities or tasks in the project which could delay the entire
                                           project if they were not completed on time?
                                       3.  Is the project on schedule, behind schedule or ahead of schedule?
                                       4.  If the project has to be finished earlier than planned, what is the best way to do this
                                           at the least cost?

                                    9.2.3 The Framework for PERT and CPM

                                    Essentially, there are six steps which are common to both the techniques. The procedure is listed
                                    below:
                                    1.   Define the Project and all of it’s important activities or tasks. The Project (made up of
                                         several tasks) should have only a single start activity and a single finish activity.

                                    2.   Develop the relationships amongst the activities.  Decide which  activities must precede
                                         and which must follow others.
                                    3.   Draw the “Network” connecting all the activities. Each Activity should have single event
                                         numbers. Dummy arrows are used where required to avoid giving the same numbering
                                         to two activities.

                                    4.   Allot time and/or cost estimates to each activity
                                    5.   Compute the longest time path during the network. This is called the critical path.
                                    6.   Use the Network to help plan, schedule, monitor and control the project.
                                    The Key Concept used by CPM/PERT is that a petite set of activities, which make up the longest
                                    path through the activity network control the entire project. If these “critical” activities could be
                                    identified and assigned to dependable persons, management resources could be optimally used
                                    by concentrating on the few activities which determine the fate of the entire project.
                                    Non-critical activities can be replanned, rescheduled and resources for them can be reallocated
                                    flexibly, without affecting the whole project.




                                        Task    Five useful questions to ask when preparing an activity network are:
                                       1.  Is this a Start Activity?
                                       2.  Is this a Finish Activity?
                                       3.  What Activity Precedes this?
                                       4.  What Activity Follows this?

                                       5.  What Activity is Concurrent with this?

                                    Some activities are successively linked. The second activity can begin only after the first activity
                                    is completed. In certain cases, the activities are concurrent, because they are independent of each
                                    other and can start simultaneously. This is particularly the case in organisations which have
                                    supervisory resources so  that work  can be delegated to various departments  which will be
                                    responsible for the activities and their completion as planned.
                                    When work is delegated like this, the need for stable feedback and co-ordination becomes an
                                    important senior management pre-occupation.





            144                              LOVELY PROFESSIONAL UNIVERSITY
   145   146   147   148   149   150   151   152   153   154   155