Page 154 - DCAP601_SIMULATION_AND_MODELING
P. 154

Simulation and Modelling



                      Notes         Activities 1-3 and 2-4 have total float of 1 week each, represented by the solid timeline which
                                    begins at the latest start and ends at the latest finish. The difference is the float, which gives us the
                                    flexibility to schedule the activity.
                                    For example, we might send the staff on leave during that one week or give them some other
                                    work to do. Or we may choose to start the activity slightly later than planned, knowing that we
                                    have a week’s float in hand. We might even break the activity in the middle (if this is permitted)
                                    for a week and divert the staff for some other work, or declare a National or Festival holiday as
                                    required under the National and Festival Holidays Act.
                                    These are some of the examples of the use of float to schedule an activity. Once all the activities
                                    that can be scheduled are scheduled to the convenience of the project, normally reflecting resource
                                    optimisation measures, we can say that the project has been scheduled.

                                    Lab Exercise

                                    A Social Project manager is faced with a project with the following activities:
                                       Activity-id     Activity -  Description                      Duration

                                       1-2             Social Work Team to live in Village          5 Weeks
                                       1-3             Social Research Team to do survey            12  Weeks
                                       3-4             Analyse results of  survey                   5 Weeks

                                       2-4             Establish Mother & Child Health Program      14  Weeks
                                       3-5             Establish Rural Credit  Programme            15  Weeks

                                       4-5             Carry out Immunisation of Under Fives        4 Weeks
                                    1.   Draw the arrow diagram, using the helpful numbering of the activities, which suggests
                                         the following logic:
                                    2.   Unless the Social Work team lives in the village, the Mother and Child Health Programme
                                         cannot be started due to ignorance and superstition of the villagers
                                    3.   The Analysis of the survey can obviously be done only after the survey is complete.
                                    4.   Until rural survey is done, the Rural Credit Programme cannot be started

                                    5.   Unless Mother and Child Programme is established, the Immunisation of Under Fives
                                         cannot be started
                                         Calculate the Earliest and Latest Event Times

                                         Tabulate and Analyse the Activities
                                         Schedule the Project using a Gantt Chart

                                    The PERT (Probabilistic) Approach

                                    So far we have talked about projects, where there is high assurance about the outcomes of
                                    activities. In other words, the cause-effect logic is well known. This is particularly the case in
                                    Engineering projects.
                                    However, in Research & Development projects, or in Social Projects which are defined as “Process
                                    Projects”, where learning is an significant outcome, the cause-effect relationship is not so well
                                    established.





            148                              LOVELY PROFESSIONAL UNIVERSITY
   149   150   151   152   153   154   155   156   157   158   159