Page 156 - DCAP601_SIMULATION_AND_MODELING
P. 156

Simulation and Modelling



                      Notes         In Activity 1-3, the time estimates are 3,12 and 21. Using our PERT formula, we get:





                                                           The Standard Deviation (s.d.) for this activity is also calculated using
                                                           the PERT formula

                                    We calculate the PERT event times and other details as below for each activity:




                                         Event   to   tm   tp   te   ES   EF   LS   LF   TF   s.d.   Var.
                                          1-3   3    12   21   12   0   12   0   12   0   3          9

                                          3-5   6    15   30   16   12   28   12   28   0   4       16



                                          1-2   2    5   14   6   0    6    5   11   5    2          4

                                          2-4   5    14   17   13   6   19   11   24   5   2         4
                                          3-4   2    5    8   5   12   17   19   24   7   1          1

                                          4-5   1    4    7   4   19   23   24   28   5   1          1



                                    Estimating Risk

                                    Having calculated the s.d. and the Variance, we are prepared to do some risk analysis. Before
                                    that we should be aware of two of the most important assumptions made by PERT.

                                    1.   The Beta distribution is suitable for calculation of activity durations.
                                    2.   Activities are independent, and the time necessary to complete one activity has no bearing
                                         on the completion times of it’s successor activities in the network. The validity of this
                                         assumption  is  questionable  when we  consider that  in practice,  many activities have
                                         dependencies.

                                    9.2.5 Expected Length of a Project

                                    PERT assumes that the expected length of a project (or a sequence of independent activities) is
                                    purely the sum of their separate expected lengths.
                                    Therefore the summation of all the t ’s along the critical path gives us the length of the project.
                                                                 e
                                    Likewise the variance of  a sum  of independent  activity times is  equal to the sum of their
                                    individual variances.
                                    In our instance, the sum of the variance of the activity times along the critical path, VT is found
                                    to be equal to (9+16) = 25.







            150                              LOVELY PROFESSIONAL UNIVERSITY
   151   152   153   154   155   156   157   158   159   160   161