Page 161 - DCAP601_SIMULATION_AND_MODELING
P. 161

Unit 9: Simulation of a PERT Network (I)



                                                                                                  Notes
                 Example:  When building a house, the land must be graded before the foundation can be
            laid)

                 Example: In the following example there are seven tasks, labeled A through G. Some tasks
            can be done concurrently (A and B) while others cannot be done until their predecessor task is
            complete (C cannot begin until A is complete). Additionally, each task has three time estimates:
            the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic
            time estimate (P). The expected time (T ) is computed using the formula (O + 4M + P) ÷ 6.
                                           E
              Activity  Predecessor              Time  estimates            Expected time

                                     Opt.  (O)    Normal  (M)    Pess.  (P)
              A             —           2              4            6        4.00
              B             —           3              5            9        5.33

              C             A           4              5            7        5.17
              D             A           4              6           10        6.33
              E            B, C         4              5            7        5.17

              F             D           3              4            8        4.50
              G             E           3              5            8        5.17

            Once this step is complete, one can draw a Gantt chart or a network diagram.












            A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the
            slack is the black lines connected to non-critical activities, (3) since Saturday and Sunday are not
            work days and are thus excluded from the schedule, some bars on the Gantt chart are longer if
            they cut through a weekend.
























                                             LOVELY PROFESSIONAL UNIVERSITY                                  155
   156   157   158   159   160   161   162   163   164   165   166