Unit 9: Simulation of a PERT Network (I)



            3.   The Latest Finish is the value in the diamond at the head of each activity       Notes

            4.   The Latest Start is = Latest Finish - Duration
            There are two significant types of Float or Slack. These are Total Float and Free Float.
            TOTAL FLOAT is the spare time available when all earlier activities occur at the earliest possible
            times and all succeeding activities occur at the latest possible times.
            Total Float = Latest Start - Earliest Start
            Activities with zero Total float are on the Critical Path

            FREE FLOAT is the spare time available when all previous activities occur at the earliest possible
            times and all succeeding activities occur at the earliest possible times.
            When an activity has zero Total float, Free float will also be zero.

            There are a variety of other types of float (Independent, Early Free, Early Interfering, Late Free,
            Late Interfering), and float can also be negative. We shall not go into these situations at present
            for the sake of simplicity and be concerned only with Total Float for the time being.

            Having calculated the  various parameters of each activity, we are now ready to go into the
            scheduling phase, using a type of bar chart known as the Gantt Chart.
            There are various extra types of float (Independent, Early Free, Early Interfering, Late Free, Late
            Interfering), and float can also be negative. We shall not go into these situations at present for
            the sake of plainness and be concerned only with Total Float for the time being. Having computed
            the various parameters of each activity, we are now ready to go into the scheduling phase, using
            a type of bar chart known as the Gantt Chart.




              Did u know?  What is the difference between Total Float and Free Float?
              Total Float is the spare time available when all preceding activities occur at the earliest
              possible times and all succeeding activities occur at the latest possible times.

              Free Float is the spare time available when all preceding activities occur at the earliest
              possible times and all succeeding activities occur at the earliest possible times.

            Scheduling of Activities using a Gantt Chart

            Once the activities are laid out along a Gantt Chart (Please see chart below), the concepts of
            Earliest Start & Finish, Latest Start & Finish and Float will become very obvious.