                    Notes                       Table 6.1: Statement of Fixed, Variable and Total Costs and Per Unit

                                      S.No.  Units  Fixed   Fixed Cost   Variable   Variable Cost   Marginal Cost   Total
                                                  Cost (`)  per unit (`)  Cost (`)  per unit (`)  (`) ΔC/ΔU  Cost (`)
                                      1.     1     500        500       10           10          10     510
                                      2.     50    500        100       500          10          10    1000
                                      3.     100   500          5      1000          10          10    1500
                                      4.     150   500       3.333     1500          10          10    2000


                                   Fixed Cost: It is a cost remains constant or fixed irrespective level of production.

                                          Example: Rent ` 5,00/- is to be paid irrespective level of production. It remains constant/

                                   fixed irrespective of changes taken place on the level of production.
                                                                     Figure 6.1

                                                  Y’


                                                                                           Total Fixed Cost Line



                                                                                       Fixed Cost per unit Line


                                                                                            X’

                                            X’- Units                                   Y’- Cost in Rupees

                                   Variable cost: It is a cost, which varies with level of production.

                                                                     Figure 6.2
                                                                                       Variable Cost



                                                                                                                                                Variable Cost per unit







                                           X’ - Units                   Y’ -  Cost in Rupees
                                   The following are the various components of variable cost:
                                   1.   Direct Materials: Materials cost consumed for the production of goods.
                                   2.   Direct Labour: Wages paid to the labourers who directly involved in the production of
                                       goods.
                                   3.   Direct Expenses: Other expenses directly involved in the production stream.

                                   4.   Variable portion of Overheads:  Generally the overheads can be classified into two
                                       categories, viz. Variable overheads and Fixed overheads.
                                   The variable overheads is the cost involved in the procurement of indirect materials, indirect
                                   labour and indirect expenses.