Page 280 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 280

Unit 14: Operations Scheduling




          subtracting the  times associated with producing  that order,  including  material  delivery,  Notes
          production, and shipping. These calculations resulted in a start date for that customer order. This
          process, called backward scheduling, is an approach based on averages, it doesn’t consider the
          daily fluctuations and operating factors and conditions on the factory floor.

          14.1  Scheduling

          Scheduling is the problem of assigning a set of tasks to a set of resources subject to a set of
          constraints.


                 Example: scheduling constraints include deadlines (e.g., job ‘i’ must be completed by
          time ‘t’), resource capacities (e.g., there are only four drills), precedence constraints on the order
          of tasks (e.g., a piece must be sanded before it is painted), and priorities on tasks (e.g., finish job
          ‘j’ as soon as possible while meeting the other deadlines).


                 Example:  scheduling  domains  include  classical  job-shop,  manufacturing,  and
          transportation scheduling.
          The early 1960s saw the emergence of the concept of MRP. It used backward scheduling to
          highlight material shortages and then generate production and purchase orders to avoid those
          shortages. With the emergence of IT, the computerization of MRP automated the process and
          work  associated with  material requisition. These new tools  rekindled  the interest in  plant
          scheduling problem and a new system, MRP II, emerged.
          MRP II introduced the concept called the Master Production Schedule (MPS). MPS was a layer
          added on top of MRP. It also marked the end of ordering inventory based on past usage. Instead,
          MPS focused on sales and marketing’s best guess of the future need for products. This best guess
          was then passed to the next planning function, namely, the next MRP run. Both MRP and MPS
          assume certain ideal characteristics about the imperfect world of production and the plant floor:

              Infinite resources (machine capacity and labour) are always available and do not change.
              Material resources will arrive  as scheduled in the  right quantities. Any variances,  or
               missed incoming shipments, were expedited manually until the next MRP run.

              Customer orders and products have the same priority. MRP aggregates demand (customer
               orders) into lots and outputs.

              Lead times (production and material delivery) are fixed or proportional to lot size.
              Scheduling on a weekly basis will meet planning requirements.
          Scheduling starts with the Master Production Schedule (MPS), which defines current and future
          (forecasted) resource requirements based on current and forecasted customer orders. Completing
          these orders is the goal—the MPS provides production targets toward reaching that goal. In
          doing so, it takes into account the technical requirements of the task and available capacity and
          matches it with the forecasted demand. Everything else in the planning system works from the
          MPS. The result is a set of purchasing and manufacturing orders with start and due dates, and a
          list of the minimum quantities of inventory to satisfy the MPS.

          The  planning system  also initiates  operations scheduling  through  capacity  requirements
          planning.

              It starts by determining whether the enterprise has the production capacity available to
               build what’s listed in the MPS.




                                           LOVELY PROFESSIONAL UNIVERSITY                                   275
   275   276   277   278   279   280   281   282   283   284   285