Page 124 - DMGT302_FUNDAMENTALS_OF_PROJECT_MANAGEMENT
P. 124

Unit 7: Project Scheduling



            Framework for PERT and CPM                                                            Notes

            Essentially, there are six steps which are common to both the techniques. The procedure is listed
            below:
            1.   Define the Project and all of it’s significant activities or tasks. The Project (made up of
                 several tasks) should have only a single start activity and a single finish activity.
            2.   Develop the relationships among the activities. Decide which activities must precede and
                 which must follow others.
            3.   Draw the “Network” connecting all the activities. Each Activity should have unique event
                 numbers. Dummy arrows are used where required to avoid giving the same numbering
                 to two activities.
            4.   Assign time and/or cost estimates to each activity.
            5.   Compute the longest time path through the network. This is called the critical path.
            6.   Use the Network to help plan, schedule, monitor and control the project. The Key Concept
                 used by CPM/PERT is that a small set of activities, which make up the longest path
                 through the activity network control the entire project. If these “critical” activities could
                 be identified and assigned to responsible persons, management resources could be
                 optimally used by concentrating on the few activities which determine the fate of the
                 entire project.
            Non-critical activities can be replanned, rescheduled and resources for them can be reallocated
            flexibly, without affecting the whole project. Five useful questions to ask when preparing an
            activity network are:
            1.   Is this a Start Activity?
            2.   Is this a Finish Activity?
            3.   What Activity Precedes this?
            4.   What Activity Follows this?
            5.   What Activity is Concurrent with this?
            Some activities are serially linked. The second activity can begin only after the first activity is
            completed. In certain cases, the activities are concurrent, because they are independent of each
            other and can start simultaneously. This is especially the case in organisations which have
            supervisory resources so that work can be delegated to various departments which will be
            responsible for the activities and their completion as planned.
            When work is delegated like this, the need for constant feedback and coordination becomes an
            important senior management preoccupation.
            Drawing the CPM/PERT Network


            Each activity (or sub-project) in a PERT/CPM Network is represented by an arrow symbol. Each
            activity is preceded and succeeded by an event, represented as a circle and numbered.




















                                             LOVELY PROFESSIONAL UNIVERSITY                                  119
   119   120   121   122   123   124   125   126   127   128   129