Unit 7: Project Scheduling



            The probability associated with Z= +1 is 0.84134. This is a strong probability, and indicates that  Notes
            the odds are 16 to 3 that the project will be completed by the due date.




























            If the probability of an event is p, the odds for its occurrence are a to b, where:

                                         a   p   0.84134  16
                                          =     =       =
                                         b  1 − p  0.15866  3
            Self Assessment


            Fill in the blanks:

            9.    Activities with zero Total float are on the ....................... Path.
            10.  ....................... is the spare time available when all preceding activities occur at the earliest
                 possible times.
            11.  The ....................... distribution is appropriate for calculation of activity durations.

            12.  ....................... assumes that the expected length of a project is simply the sum of their
                 separate expected lengths.

            13.  The sum of the ....................... of the activity times along the critical path.

            14.  The square root ....................... gives us the standard deviation of the project length.
            15.  A random variable drawn from a Normal Distribution has ....................... probability of
                 falling within one standard deviation of the distribution average.
            16.  The ....................... of the variance of the activity times along the critical path.