Page 157 - DMGT302_FUNDAMENTALS_OF_PROJECT_MANAGEMENT
P. 157

Fundamentals of Project Management



                      Notes         The following sections describe the activities required to perform project closure.




                                        Task  Discuss about project termination

                                    9.5 Perform Project Closure


                                    To initiate the closure of the project, a project closure report should first be created. This report
                                    lists all of the closure activities and identifies the resource responsible for each activity listed.
                                    Following the approval of the report by the customer, the activities identified are actually
                                    undertaken to close the project.

                                    Document a Project Closure Report

                                    A project closure report is a document which formalizes the closure of a project. It provides
                                    confirmation that the criteria for customer acceptance have been met and requests sign-off from
                                    the project sponsor to close the project. A project closure report includes:
                                    1.   a detailed list of project completion criteria;

                                    2.   confirmation that all completion criteria have been met;
                                    3.   a list of outstanding business activities, risks and issues;
                                    4.   a set of actions to hand over project deliverables and documentation, terminate supplier
                                         agreements, release resources to the business and inform stakeholders of the closure;
                                    5.   a request for project closure approval.
                                    A project closure report is prepared at the start of the project closure phase by the project
                                    manager and is submitted to the project sponsor for sign-off. Following sign-off, a suite of
                                    closure activities are undertaken to formally close out the project.
                                    The following sections describe how to create a project closure report, providing tables and real
                                    life examples used for projects.

                                    Validate the Project Completion

                                    This section confirms that the criteria required to complete the project have been met and that
                                    any outstanding items have been identified.

                                    Completion Criteria

                                    The first step towards initiating project closure is to confirm that the project completion criteria
                                    have been achieved. List the project completion criteria in Table 9.1 and for each criterion listed,
                                    confirm whether or not it has been approved by the customer.

                                                              Table 9.1: Completion Criteria









                                                                                                           Contd...