Unit 13: PERT, CPM and Time Estimation




          crash. Hence, it is crashed. The project network after this crashing is shown in Figure 13.8. As per  Notes
          this Figure 13.8, the critical path is (1-2-4-6-7) with a duration of 2014 weeks and the total direct
          cost is   56,400.

                                   Figure 13.8: Project Network (6)


                                      6                    3
                         2                       4                      6

                                                                               7
                 4
                                       5                          2


              1                                                                  7
                                                                         9
                       5
                                                5
                                  3                          5



          Looking at the new critical path (1-2-4-6-7) we find that the only non crashed activity is (4-6).
          Crashing this gives us the project network shown in Figure 13.9. As per this Figure 13.9, the
          critical path again is (1-2-4-6-7) with a duration of 191/2  weeks and  the total direct cost is
            57,600.
                                   Figure 13.9: Project Network (7)



                                     6                    2
                         2                      4                     6
                                                                             7
                    4
                                      5
                                                                 2

               1                                                               7

                                                                       9
                       5
                                              5
                                   3                        5




          Since all the activities on the critical path (1-2-4-6-7) are crashed, there is no possibility of further
          time reduction.

          From Table 13.2, we find that the total cost is minimized for the project schedule represented by
          the activities crashed are (1-2), (2-4), (3-5), (5-6), (6-7). The information provided in Table 13.2 is
          useful for decision-making.