                                      Task  Describe the steps for Drawing the PERT/CPM Network.
                                   The Backward Pass - Latest Finish Time Rule


                                   To make the Backward Pass, we begin at the sink or the final event and work backwards to the
                                   first event.

                                                  Figure 13.13: Backward Pass and Latest Finish Time Rule





















                                   At Event 3 there is only one activity, Activity 3-4 in the backward pass, and we find that the value
                                   is 11-7 = 4 weeks. However at Event 2 we have to evaluate 2 activities, 2-3 and 2-4. We find that
                                   the backward pass through 2-4 gives us a value of 11-6 = 5 while 2-3 gives us 4-0 = 4. We take
                                   the smaller value of 4 on the backward pass.
                                   Self Assessment


                                   State True or False:
                                   14.  Planning, Scheduling and Control are considered to be advanced Managerial functions.
                                   15.  There are many variations  of PERT/CPM  which have  been useful  in planning  costs,
                                       scheduling manpower and machine time.
                                   16.  Non-critical activities can  be  replanned,  rescheduled and  resources for  them can  be
                                       reallocated flexibly.
                                   17.  Each activity in a PERT/CPM Network is represented by a circle symbol.

                                   13.9 Tabulation and Analysis of Activities

                                   We are now ready to tabulate the various events and calculate the Earliest and Latest Start and
                                   Finish times. We are also now ready to compute the SLACK or TOTAL FLOAT, which is defined
                                   as the difference between the Latest Start and Earliest Start.