Page 25 - DMGT521_PROJECT_MANAGEMENT
P. 25

Project Management




                    Notes            each other. But if the BPM doesn’t have the required  project management capabilities
                                     there can be a conflict of authority: the BPM is in charge - the “boss” - but the IT PM needs
                                     to tell them what to do and how to do it. Hoping that the BPM and IT PM will complement
                                     each other and work well together is not enough, we have seen this go bad a large number
                                     of times. Roles and responsibilities, especially for the project management tasks, is the
                                     foundation of a project and if that goes wrong it is very difficult to correct. So it’s best to
                                     get it right at the start. Having more than one person in a project with a role of “project
                                     manager” is confusing. There should only be one. This can be resolved by only giving the
                                     overall project manager this role and the IT PM is called an “IT work stream lead” or “IT
                                     team lead”. Some IT project managers have great difficulty accepting this; after all it says
                                     “Project Manager” on their business card, and they expect that to appear as their role in
                                     every project as  well. Of  course a project role  and a job title are completely  different
                                     things,  but we have found that this “role inflation” has crept into the way people see
                                     project roles. My goal was to ensure that when a project was setup, it had a good foundation
                                     to be successful. Of course the project team members still need to work together well to be
                                     successful, but giving the team a good  foundation allows them to  focus on delivering
                                     together, instead of trying to work out who they should listen to. I started looking for a
                                     solution to this dilemma.
                                     What did I Find?

                                     My analysis led me to the conclusion that we needed a capable and experienced project
                                     manager to  be responsible  for the  project management,  and someone with the  right
                                     authority and “organisational credit” to be responsible for the change in the business. As
                                     the experienced project managers available for our IT projects are nearly always from IT
                                     they do not have the authority or credit in the customer’s organisation. And the main
                                     customer contacts, the potential candidates for the BPM role, often don’t have the project
                                     management capabilities. Looking at how MSP describes the programme structure, the
                                     key players are the SRO (Senior Responsible Owner), the Programme Manager and the
                                     BCM (Business Change Manager). The key here is that the BCM does not report to the
                                     Programme Manager or vice versa; and that the Programme Manager is responsible for
                                     the day-to-day management of the programme while the BCM is responsible for delivering
                                     change and benefits. Why couldn’t this work in a project as well? With a team of project
                                     managers I worked through the roles and responsibilities in a typical project, with the aim
                                     of making this work.  The project  managers  were motivated in  this too,  as they  had
                                     experienced the problem first hand! The result was a proposed project structure as shown
                                     in figure 1.

                                                          Figure 1:  Proposed  Project  Structure

                                                                 Corporate Management

                                                                 Project Steering Group
                                                          Senior User  Sponsor  Senior Supplier


                                                                BCM          PM

                                                             Change Agents  Team Members
                                                                     = from the customer
                                                                     = from the supplier(s)
                                                                     = delivery specialists

                                                                                                         Contd...



          20                                LOVELY PROFESSIONAL UNIVERSITY
   20   21   22   23   24   25   26   27   28   29   30