Unit 13: Special Economic Zones



            For setting up SEZ, the interested party has to fill up an application with the name, address, and  Notes
            status of the developer and co-developer. The developer is also required to submit a project
            report with details about the proposed location of SEZs, details of infrastructure that already
            exists, details of infrastructure that will be established, and the total area of the proposed SEZ.
            The project report of the proposed SEZ that will be submitted along with the application form
            should also contain investment details, which would include the financing mode and the project’s
            viability. It should also contain details as to whether the proposed SEZ would be a multi-
            product or specific industries zone and foreign equity details. The application, along with the
            project report for the setting up of an SEZ unit, is submitted to the Chief Secretary of the State.

                         Table 13.4 Approval Procedure of Setting up an SEZ in India

                              Proposal by person   Proposal may also be made directly to the
                    Form-A
                              intending to set up   board; after approval by the board, the person
                              SEZ to the concerned   will require to obtain state government
                   First Step   state government   concurrence within a period of 6 months.
                                      The state government  Within 45 days; the state government to
                   Second Step    forwards the proposal   ensure that requirements of minimum land
                                                area, and the exemption of taxes at state
                              along with its
                              recommendations to   level, delegation of powers to DC as
                              the board         recommended are made available to
                   Third Step                   developer and units
                              Approval or refusal by  The board may approve the proposal with or
                              board             without modifications, or reject it. In practice,
                                                the board accords in-principal approval
                                                pending land acquisition in Form B-1
                   Form-B     Issuance of letter of   Within 30 days of receipt of BOA
                              approval by the   recommendation; LOA will incorporate any
                              Government of India   additional conditions imposed by the board it
                                                its recommendation. LOA validity is for 3
                                                years, during which time the developer shall
                                                take effective steps to implement the approved
                                                proposal.

            The state government in turn forwards the application to the Board of Approval, Department of
            Commerce, and Government of India. State governments have to give their commitment that
            the area where the proposed SEZ will be set up is free from all kinds of environmental restrictions
            and it would provide electricity, water, and various other services when required, and that it
            would allow transmission, generation, and power distribution inside the SEZ along with the
            application. Further, the state government has to give the commitment that it would exempt the
            proposed SEZ from sales tax, turnover tax, and Mandi tax on the goods supplied from the area of
            domestic tariff to the units in the SEZ. Also, the government of the state has to give the commitment
            that it would declare the units of the SEZ as public utility service and that the system of single
            point clearance and minimum inspection would be provided to the SEZs. The Board of Approval
            will consider such application forwarded to it by state governments and will issue a permission
            letter or refusal note to the developer of SEZ and also inform the state government.
                          Table 13.5: Who’s Who in SEZ Approval Committee (BOA)












                                                                                   Contd...