                                  9.1.2 Drawing the CPM/PERT Network


                                  Each activity  (or sub-project)  in a PERT/CPM Network  (see figure 9.1) is represented by an
                                  arrow symbol. Each activity is preceded and succeeded by an event, represented as a circle and
                                  numbered.

                                                               Figure  9.1: CPM  Network






















                                                                    PERT











                                  At Event 3, we have to evaluate two predecessor activities - Activity 1-3 and Activity 2-3, both of
                                  which are predecessor activities. Activity 1-3 gives us an Earliest Start of 3 weeks at Event 3.
                                  However, Activity 2-3 also has to be completed before Event 3 can begin. Along this route, the
                                  Earliest Start would be 4 + 0 = 4. The rule is to take the longer (bigger) of the two Earliest Starts.
                                  So the Earliest Start at event 3 is 4.
                                  Similarly, at Event 4, we find we have to evaluate two predecessor activities - Activity 2-4 and
                                  Activity 3-4. Along Activity 2-4, the Earliest Start at Event 4 would be 10 wks, but along Activity
                                  3-4, the Earliest Start at Event 4 would be 11 wks. Since 11 wks is larger than 10 wks, we select it
                                  as the Earliest Start at Event 4. We have now found the longest path through the network. It will
                                  take 11 weeks along activities 1-2, 2-3 and 3-4. This is the Critical Path.



                                     Did u know?  CPM was the discovery of M.R. Walker of E.I. Du Pont de Nemours & Co. and
                                     J.E. Kelly of Remington Rand, circa 1957. The computation was designed for the UNIVAC-
                                     I computer. The first test was made in 1958, when CPM was applied to the construction of a




          168                               LOVELY PROFESSIONAL UNIVERSITY
   169   170   171   172   173   174   175   176   177   178   179