                    Notes          Critical Chain approach is perhaps the most important new development in project scheduling
                                   in the last 30 years. Used properly, the Critical Chain approach is an extremely powerful means
                                   of gaining more predictability, productivity and speed from your project plans. It has  been
                                   found to be an effective tool to protect projects from uncertainty.




                                      Task  Explain in a group of four in your words that by using the Critical Chain Method,
                                     how the projects can be completed more quickly?
                                   Self Assessment


                                   Fill in the blanks:
                                   5.  CCPM (Critical Chain Project Management) puts more emphasis on the resources required
                                       to …………………….. project.

                                   6.  …………………… durations  (providing worst-case estimates) is done to ensure a high
                                       probability of task completion.
                                   7.  Critical  Chain  approach  is  perhaps  the  most  important  new  development  in
                                       ……………………. in the last 30 years.

                                   9.3 Critical Chain Project Management Approach

                                   The CCPM approach is identical to the TPM approach up to the point where the project network
                                   diagram is defined and the critical path is identified. The traditional project manager would next
                                   conduct a resource leveling exercise targeting resource usage on the critical path. At this point,
                                   the critical chain project manager develops the critical chain plan. In the discussion that follows,
                                   we describe each of the CCPM planning steps for you by way of a simple example. We will use
                                   as an example the project shown in Figure 9.2.

                                   Step 1: Creating the Early Schedule Project Network Diagram

                                   Figure 9.2 shows the early schedule for a simple seven-task project same as TPM might make.

                                                               Figure  9.2:  The  Early  Schedule