Page 175 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 175

Unit 9: CPM /PERT




             new chemical plant. In March 1959, the method was applied to a maintenance shutdown at  Notes
             the Du Pont works in Louisville, Kentucky. Unproductive time was reduced from 125 to 93
             hours.

          Self Assessment

          Fill in the blanks:
          1.   Compute the longest time path through the network. This is called the …………………...

          2.   In certain cases, the activities are…………………., because they are independent of each
               other and can start simultaneously.
          3.   Non-critical  activities can  be replanned, rescheduled and resources for  them can  be
               ………………………… flexibly, without affecting the whole project.
          4.   Use the Network to help plan, schedule, ……………………. and control the project.

          9.2 CCPM vs Traditional Project Management

          CCPM (Critical Chain Project Management) puts more emphasis on the resources required to
          execute project tasks in contrast to the more traditional Critical Path and PERT methods, which
          emphasize task order and rigid scheduling.
          Secondly, using the Critical Chain Method, projects can be completed more quickly and with
          greater scheduling reliability. The difference between traditional and Critical Chain scheduling
          is in how uncertainty is managed. In traditional project scheduling, uncertainty is managed by
          padding task durations, starting work as early as possible, multi-tasking, and focusing on meeting
          commitment  dates. The  following points  illustrate some  of  the  problems  associated  with
          traditional project scheduling:
              Padding task durations (providing worst-case estimates) is done to ensure a high probability
               of task completion. The knowledge that  there is  so much  safety time built into  tasks
               results in various time wasting practices, e.g., waiting until the last moment to complete
               a task. As a result, all the safety time can be wasted at the  start of  the task  so that,  if
               problems are encountered, the task overruns.

              Starting work as early as possible, even when not scheduled, is a response to worst-case
               estimates. When workers give worst-case estimates, they don’t expect to stay busy with just
               one task – so they multi-task, working on several tasks at once by switching between them.
               The result is that everything takes a long time to complete and very little completes early.
              With  the focus  on meeting commitment dates  (start and  finish), output  from  a  task
               completed early will rarely be accepted early by the next person needing this output. So,
               any effort spent in finishing early will be wasted.
          Given the above issues, the most projects are always late.

          In critical chain scheduling, uncertainty is primarily managed by:
          (a)  using average task duration estimates
          (b)  scheduling backwards from the date a project is needed (to ensure work that needs to be
               done is done, and it is done only when needed)
          (c)  placing aggregate buffers in the project plan to protect the entire project and the key tasks
               and using buffer management to control the plan. The key tasks are those on which the
               ultimate duration of the project depends, also known as the Critical Chain.




                                           LOVELY PROFESSIONAL UNIVERSITY                                   169
   170   171   172   173   174   175   176   177   178   179   180