Page 257 - DCAP304_DCAP515_SOFTWARE_PROJECT_MANAGEMENT
P. 257

Unit 12: Monitoring & Control




                   The planned number                                                          Notes
                   The actual number
               Typical variance reports are snapshots in time (the current period) of the status of an entity
               being tracked. Most variance reports do not include data points that report how the project
               reached that status.




              Task  Project variance reports can be used to report project as well as activity variances.
             Explain in group of four.

          12.7.2  How and What Information to Update

          As input to each of these report types, activity managers and the project manager must report
          the progress made on all of those activities that were open for work during the period of time
          covered by the status report. Recall that your planning estimates of activity duration and cost
          were  based on little or no information. Now that  you  have  completed some  work on  the
          activity, you should be able to provide a better estimate of the duration and cost exposure. This
          reflects itself in a re-estimate of the work remaining to  complete the  activity. That  update
          information should also be provided.
          The following is a list of what should actually be reported:

          1.   Determine a set period of time and day of week by which by which all updated information
               is to be submitted.

          2.   Report actual work accomplished during this period.
          3.   Record historical and re-estimate remaining (in-progress work only).
          4.   Actual start and finish dates of activities started or completed during the report period.

          5.   Record days of duration accomplished of so far working re-estimated duration as reflected
               in the time-to-completion number.

          6.   Report resource effort (hours/day) spent and remaining (in-progress work only).


             Did u know?  What is Frequency of Gathering and Reporting Project Progress?

             A logical frequency for reporting project progress  is once a week,  usually on Friday
             afternoon. There are some projects, such as refurbishing a large jet airliner, where progress
             is recorded after each shift, three times a day.

          12.7.3  Variances

          Variances are deviations from plan. Think of a variance as the difference between what was
          planned and what actually occurred. There are two types of variances:

          Positive Variances

          Positive variances are deviations from plan that indicate that an ahead-of-schedule situation has
          occurred or that an actual cost was less than a planned cost. This type of variance is good news to
          the project manager.




                                           LOVELY PROFESSIONAL UNIVERSITY                                   251
   252   253   254   255   256   257   258   259   260   261   262