Unit 12: Monitoring & Control




                                                                                                Notes
                               Figure 12.9:  A Typical  Milestone  Trend  Chart



























          12.8.1 Using the WBS to Report Project Status

          Because the Work Breakdown Structure (WBS) shows the hierarchical structure of the work to be
          done, it can be used for status reporting, too. In its simplest form, each activity box can be shaded
          to reflect completion percentages. As lower-level activities are completed, the summary activities
          above them can be shaded to represent percent complete data. Senior managers will appreciate
          knowing that major parts of the project are complete. Unfortunately, the WBS does not contain
          scheduling or sequencing information. To the extent that this adds to the value of the report,
          narrative data or brief tabular data might be added to the report. Figure 12.10 shows an example
          status report using the WBS.

                               Figure 12.10:  Status Reporting  with the  WBS