                    Notes          Taking all these time estimates into consideration, the expected time of an activity is arrived at.
                                   The average or mean (t ) value of the activity duration is given by,
                                                     a
                                                                           
                                                                                                            (5)

                                   The variance of the activity time is calculated using the formula,

                                                                          
                                                                                                         (6)
                                                                          

                                   Probability for Project Duration

                                   The probability of completing the project within the scheduled time (T ) or contracted time may
                                                                                           s
                                   be obtained by using  the standard normal deviate where T   is the expected  time of project
                                                                                    e
                                   completion.

                                                                                                            (7)
                                                                     

                                   Probability of completing the project within the scheduled time is,
                                                      P (T< T ) = P ( Z< Z  ) (from normal tables)           (8)
                                                            s         0

                                        Example: An R&D project has a list of tasks to be performed whose time estimates are
                                   given in the Table 12.8, as follows.

                                   Time expected for each activity is calculated using the formula (5):
                                                                       
                                                           T =
                                                            a

                                                                     
                                                             =              =   = 6 days for activity A

                                   Similarly, the expected time is calculated for all the activities.
                                   The variance of activity time is calculated using the formula (6).

                                                                      
                                                            =        
                                                                      

                                                                    
                                                             =        = 0.444
                                                                    
                                   Similarly, variances of all the activities are calculated. Construct a network diagram and calculate
                                   the time earliest, T  and time Latest T  for all the activities.
                                                  E              L