          be planned accurately with the help of mathematical calculations. This planning of work-in-  Notes
          progress of the finished goods is known as Material Requirement Planning  (or MRP).





             Notes  While doing Material Requirement Planning  one has to look for the following
             things:
             1.  All the components, sub-assemblies and assemblies are known so that they all can
                 participate for the planning  of required materials.

             2.  The lead time of all the assemblies and sub-assemblies should be known.
             3.  The  inventory already  in hand should be  considered for  the present  Material
                 Requirement Planning.

          13.4.2 The MRP Process

          The MRP process is initiated once the customer orders for the finished goods from the supplier.
          Then the forecasting is done for the finished goods. A master plan is prepared for the production
          process. This master plan contains  all the constituents of the production process that would
          finally lead to the resultant product.

                                            Figure  13.1






































          The master plan for production initiates the process of Material  Requirement Planning. For
          MRP two  other inputs  are  inventory  which  is  already in  hand  and  product  design  and
          development. Then we have to see whether the capacity is adequate for the production  of
          requisite number of finished goods demanded by the customer. If the answer is negative, then
          again we have to reschedule our production plan. But if the answer is affirmative i.e., there is