Page 143 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 143

Production and Operations Management




                    Notes             Direct costs include labour, materials, equipment and any other costs directly related to
                                       project activities.

                                      Indirect costs include  administration, depreciation,  financial costs, and other  variable
                                       overheads. Indirect costs can be avoided by reducing total project time. The shorter the
                                       duration of the project, the lower will be the indirect costs.
                                      Penalty clauses are often part  of project  contracts if the project  extends beyond  some
                                       specific date. Sometimes a bonus may be provided for early completion. Some activities
                                       can be expedited to reduce overall project completion time and total project costs.

                                   Time cost Trade-off procedures make use of some special terms. Some of these are explained
                                   here below:

                                   Normal Activity Time-Cost-Point

                                   Is  the  lowest  point  on  a  time-cost  graph  and  represents  the  absolute  minimum  cost  for
                                   accomplishing the activity in  normal time. Normal Time  is the shortest time to perform the
                                   activity within the constraint of minimum direct cost.
                                   Feasible Activity Time-Cost Trade-Off Points


                                   Represent  the various combinations of minimum direct  costs and  their corresponding least
                                   timings for one individual activity only. There can be few or several of these points and they can
                                   be best represented on a graph showing cost versus timings:
                                   (i)  The project duration is too long.
                                   (ii)  The customer wants to know the additional costs for saving part of the project completion
                                       time.
                                   (iii)  The company may like  to minimize the sum of direct  and indict project costs without
                                       disturbing the stipulated duration time.
                                   Because the project indirect costs can be easily determined through existing accounting practices,
                                   Time-Cost Trade-off procedures are mostly used  for minimizing direct  costs for the  given
                                   project duration times only.

                                   The procedure for ‘Feasible Activity Time Cost Trade-off’ consists in collecting first cost data for
                                   the network and rescheduling of all the critical and near critical activities, again collecting
                                   second cost data and rescheduling the new critical or sub-critical activities and so on. A systematic
                                   procedure has been developed by Burgess.
                                      Starting with the bottom activity, the method makes comparisons between the sums of
                                       squares of daily resource requirements and selects the one with minimum sum.
                                      The target always being toward reducing the project duration time with minimum increase
                                       Direct Costs.

                                      The process is continued till a step is reached when increase in Direct Cost is less than the
                                       decrease in Indirect Costs. That means no further decrease in Total Costs is possible.

                                      This method of choosing the schedule, leads to the least variation in resource requirements.
                                       This is also called ‘crashing’.







          138                               LOVELY PROFESSIONAL UNIVERSITY
   138   139   140   141   142   143   144   145   146   147   148